PRC-029-1 and PRC-024-3: Why They Are Not the Same Standard
Both standards address IBR ride-through during grid disturbances, but the compliance obligations they impose are fundamentally different
The Common Misconception
Inverter-based resources were previously subject to PRC-024-3, which addressed frequency and voltage ride-through for a broad range of generating technologies including IBRs. PRC-029-1 was developed specifically for IBRs and replaced PRC-024-3 as the applicable standard for those facilities. A common assumption is that PRC-029-1 is simply an updated version of PRC-024-3 for IBRs. It is not.
The two standards share a common goal: keeping generating facilities connected during grid disturbances. Beyond that, the compliance obligations differ in scope, analytical approach, and practical complexity. Key differences include:
- How the ride-through obligation is framed: no-trip zones versus must-ride-through zones with performance requirements
- What analytical work is required to demonstrate compliance
- The complexity of the protection hierarchy that must be evaluated
- Constraints introduced by inverter firmware with no equivalent in relay-based protection
- A broader applicability threshold that captures facilities below the BES definition
Treating PRC-029-1 as a structural equivalent of PRC-024-3 leads to compliance gaps. The sections below explain each difference.
Where the Standards Diverge
1. The Ride-Through Obligation Is Framed Differently
PRC-024-3 defines no-trip zones. PRC-029-1 defines must-ride-through zones and adds performance requirements.
- PRC-024-3: settings must not operate within defined frequency and voltage boundaries. Compliance is a settings verification exercise.
- PRC-029-1: the facility must also meet active power recovery and reactive power response requirements during and after the disturbance
- A facility that trips no protection but curtails output or injects reactive power incorrectly may still be out of compliance with PRC-029-1
2. The Analytical Work Is Fundamentally Different
PRC-024-3 compliance is demonstrated through a settings review. PRC-029-1 requires dynamic simulation.
- PRC-024-3: collect relay settings, translate to the correct voltage reference, confirm they are outside the no-trip boundary
- PRC-029-1: simulate the facility's dynamic response to each applicable fault condition using models that represent inverter control logic and protective functions
- The choice of modelling tool and inverter model fidelity are part of the compliance methodology in a way that has no parallel in PRC-024-3
3. The Protection Hierarchy Is More Complex for IBRs
PRC-024-3 evaluated protection at the machine terminals and GSU high-side. PRC-029-1 requires evaluation at multiple levels through the collection system.
- Protection functions exist at individual inverter terminals, medium-voltage collector equipment, and the plant controller
- Voltage at the inverter terminals during a fault differs from the point-of-interconnection voltage due to collector system impedance, requiring case-by-case translation
- Plant controller frequency and voltage limits must also be evaluated, as they can curtail or disconnect the entire facility independently of inverter-level protection
4. Firmware Constraints Have No PRC-024-3 Equivalent
PRC-024-3 relay settings are adjustable. IBR ride-through behavior under PRC-029-1 is governed by inverter firmware.
- Frequency pickup, voltage pickup, and time delays in discrete relay elements are generally adjustable within a defined range
- What can and cannot be adjusted in an inverter varies by manufacturer, model, and firmware version; some behavior cannot be changed without a manufacturer firmware update
- When settings cannot be freely modified, the compliance path shifts to documenting actual inverter behavior and demonstrating whether it satisfies the standard's requirements
5. PRC-029-1 Has a Broader Applicability Threshold
PRC-029-1 captures a larger population of IBR facilities than PRC-024-3 did.
- PRC-024-3 applied to BES-connected generators above defined nameplate thresholds
- PRC-029-1 adds a Category 2 classification for IBRs with aggregate nameplate greater than 20 MVA interconnecting above 60 kV, even if they do not individually qualify as BES elements
- This lower threshold reflects a reliability concern specific to IBRs: large numbers of smaller facilities tripping simultaneously can cause significant generation loss even when each individual unit has limited impact
6. Legacy Sites Face a More Complex Transition
Facilities that previously demonstrated compliance under PRC-024-3 cannot assume that compliance carries over to PRC-029-1.
- Inverter configurations acceptable under PRC-024-3 may not meet PRC-029-1 performance requirements
- Bringing legacy sites into compliance often requires firmware updates, hardware modifications, or coordination between the Generator Owner, inverter manufacturer, utility, and regional entity
- Facilities with exclusions must maintain auditable documentation identifying the exclusion and the level of the standard they can comply with
Side-by-Side Comparison
| Dimension | PRC-024-3 | PRC-029-1 |
|---|---|---|
| Ride-Through Frame | No-trip zones: settings must not operate within boundaries | Must ride-through zones plus performance requirements during and after the event |
| Core Compliance Task | Settings verification with voltage translation | Dynamic simulation of facility response to fault conditions |
| Protection Hierarchy | Machine terminals and GSU high-side | Inverter-level, collector system, and plant controller, each requiring separate evaluation |
| Setting Adjustability | Relay elements generally adjustable within range | Constrained by firmware; varies by manufacturer, model, and version |
| Applicability Threshold | BES-connected generators | BES IBRs plus Category 2 (greater than 20 MVA, greater than 60 kV interconnection) |
| Legacy Site Risk | Prior compliance does not carry over to PRC-029-1 | Full reassessment required; firmware or hardware changes may be needed |
Buyer Beware: Does Your PRC-029-1 Assessment Actually Cover the Standard?
If a PRC-029-1 scope of work, deliverable, or report from an in-house team or external consultant does not include an evaluation of facility performance under each applicable system deviation, carefully consider whether it satisfies the standard's requirements.
A PRC-029-1 assessment limited to settings verification is not complete. A complete assessment must demonstrate:
- That protection settings do not operate within the ride-through zones (the settings review component)
- That the facility's active power response meets the standard's performance requirements during and after each applicable voltage and frequency deviation
- That the facility's reactive power response meets the standard's performance requirements during and after each applicable deviation
- That protection and performance have been evaluated at both the inverter level and the plant controller level
A report that verifies ride-through settings but does not simulate and document the facility's performance response to each system deviation leaves the second half of the standard unaddressed. Under audit, that gap is a compliance finding.
Related Articles
NERC PRC-029-1 Compliance Overview
Frequency and voltage ride-through requirements for IBRs, covering what the standard requires and how TWC approaches compliance assessments.
Read more →Why Dynamic Modelling Is Required for PRC-029-1
A settings review is not sufficient for PRC-029-1. Dynamic simulation, specifically EMT modelling, provides a stronger and more technically defensible compliance basis.
Read more →NERC PRC-024 Compliance Overview
Frequency and voltage no-trip zone requirements for synchronous generators, synchronous condensers, and Type 1 and 2 wind resources.
Read more →Need a PRC-029-1 Assessment for Your IBR Facility?
TWC performs PRC-029-1 compliance engineering for inverter-based resources across North America. Contact us to discuss your facility's requirements.
Get in Touch